Revised Procedure for processing of waivers and sanctions - Online Claims: ECHS Order

Revised Procedure for processing of waivers and sanctions – Online Claims: ECHS Order

Central Organisation ECHS
Adjutant General’s Branch
Integrated HQ of MoD(Army)
Thimayya Marg,
Near Gopinath Circle
New Delhi- 110 010

B/49770/AG/ECHS/Claims/Policy

14 Dec 2021

(All Regional Centres)

REVISED PROCEDURE FOR PROCESSING OF WAIVERS AND SANCTIONS: ONLINE CLAIMS

1. Refer Cent Org ECHS letter No B/49778/AG/ECHS/Claim/Policy dt 30 Aug 2017.

2. The present procedure being followed in case of claims with discrepancy in overlapping of admission and discharge date is that the cases are examined in detail by RC and fwd to Cent Org ECHS with due justification and recommendations of Dir RC. Cent Org ECHS further gives the sanction / concurrence for processing of such claims. In more than 99% of such cases, the fault is of the first hospital by wrongly mentioning the discharge date / time due to which the second hospital is unable to upload the claim.

3. To resolve the delay in payments in cases of overlapping claims, the following amendments are suggested:-

(a) The RC will examine the case in detail consulting both the affected HCOs with due diligence. The HCOs will be given a period of 30 working days / 03 Reminders (At the end of 1st, 2nd & 3rd weeks) to respond to the queries raised by the RC.

(b) Depending upon the merit of the case, Dir RC with his recommendations will instruct the BPA to make necessary amendments in discharge time of the erring HCO and ensure necessary deduction as applicable as per the actual time of discharge.

(c) In case the first HCO (for which the claim is already settled) does not respond to the queries raised by the RC within the stipulated time period given at Para 3 (a) above, Director RC will instruct the BPA to deduct the amount equivalent to the overlap period of the settled claim of the first HCO from their subsequent claims.

(d) As per the recommendations of Dir RC, the BPA will further enable the claim processing of the second concerned hospital for which the uploading of claim is still awaited.

4. This has the approval of MD ECHS.

5. This is for your info and necessary action please. :

(K B Rana)
Surg Capt
Joint Dir (Med)
for MD ECHS

Source: ECHS Order PDF


Comments

Popular posts from this blog

Approval of the Government of India for extending the benefits of the Ayushman Bharat Pradhan Mantri Jan Arogya Yojana (AB PM-JAY) to all senior citizens aged 70 years and above.National Health Authority L.S. CHANGSAN (I.A.S.) Chief Executive Officer D. O. No. S-12018/395/2022-NHA 20th September, 2024

Grant of notional increment on 1st July I 1st January to the employees who retired from Central Govt, service on 30th June / 31st December respectively for the purpose of calculating their pensionary benefits - regarding.